Full architect's drawings for all the refurbishment work available to view on our Facebook page
Works will be carried out in small manageable phases, in sha’ Allah.
Phase 1: Basement Groundworks and Steelworks Summary [COMPLETED]
Demolish and dispose to suit new floor plan (dwg 034-100 A) |
Gutting out of all walls and cielings |
Groundwork for pillars, and major underpinning of building |
Upgrading of electric & gas Supplies |
Gutting out all of GF |
Damproofing of all external walls |
Create basement area for future potential development |
Fabricate, supply and fit new steel structure on three floors including new mezzanine floor, and associated builders’ work |
(17 tonnes of steel to create new pillars and floors and take out existing timber pillars)Build complete new ground Floor with new joists and timber flooring |
Phase 2: External Works Summary [COMPLETED]
New 3 small roofs at rear and major repair works |
Sandblasting entire building and perimeter walls |
Pointing of entire building and perimeter walls |
New aluminium gutters and downpipes throughout |
Scaffolding on all four elevations and tower |
Perimeter wall – repair and new build on Devonshire Street New aluminium windows on all the Ground Floor |
Alhamdulillah, Phase 1 & 2 and have been completed at a total cost of £190,000
Phase 3: Internal Works and Completion of Ground Floor Summary (£300,000):
Skim Finish to all external walls |
Fire -rated board & skim finish to all ceilings |
Create new fire escape door within existing window location |
WC’s Incl Shower Hose (Dwg 034-405T1) |
Raised Platform for Ablution Areas (Dwg 034-405T1) |
Ablution Seats (Dwg 034-405T1) |
Ablution Taps (Dwg 034-405T1) |
WHB’s (Dwg 034-405T1) |
Associated plumbing works (Dwg 034-405T1) |
Tiling to Kitchen Floor |
Tiling to Kitchen Splashback |
Kitchen and marble worktops |
Errect new partition walls |
Style Partitions – Flexible Walling & Glazed Wall |
New Timbers & Plywood for floor area 18mm WBP |
Ablution walls and raised platform areas |
Ablution floors and WC floors |
New Oak Floor |
Metal Design Panels |
Plumbing to wudu areas; Heating & Underfloor heating in wudu areas |
Full Electrical re-wiring & Lighting & Air Conditioning |
Audio & Visual |
CCTV |
Burgular Alarms |
S&F Mirrors in Ablution Areas |
Lowered ceilings in ablution areas using 3×2 timber and firerated boards, skim finish |
Lowered Ceiling to accommodate AC units |
External Wall & Door Blocking on Devonshire Street |
Dry-line to all walls due to allignment of internal walls |
Painting and Decorating |
Phase 4: First Floor Completion and Garden Space (Estimated amount ~ £210,000):
Details to follow…
Contact: 01535 60 77 77 | 07967 354 764Further information on all our activities visit www.abuzahra.org
Donating through JustGiving is simple, fast and totally secure. Your details are safe with JustGiving – they’ll never sell them on or send unwanted emails. Once you donate, they’ll send your money directly to the charity and make sure Gift Aid is reclaimed on every eligible donation by a UK taxpayer. So it’s the most efficient way to donate - I raise more, whilst saving time and cutting costs for the charity.
So please dig deep and donate now!